Monday, January 7, 2019

Peninsula

Rain was falling this morning, but we kept our head down and kept working.  #12 green is now officially a peninsula surrounded by dirt(and mud).  The entire green complex is getting modified.  The right side of the green went under the knife today and big progress was made.  Tarps were finally pulled from front bunkers to dry out.

We also started our prep work at #13 green.  A bunker will be constructed to the right of the green.  Unfortunately, that’s the current location of our irrigation line.  Two sprinkler heads were removed and holes dug at the end of each side of the line.  We will be trenching in a new route that will go around the bunker and reinstall the two heads.




Sod being cut to be removed






Flags marking current irrigation route on #13