Thursday, December 14, 2017
Prepped And Ready
After the dust has settled, we are ready for some sod to roll in on Friday. Six loads of soil and three loads of topsoil was brought in to get the new tees more elevated than original. Both tees are about one foot higher than original grade. The tees were laser leveled to a 1.5% slope to allow for surface drainage. A few sprinkler heads had to be raised and a drainage catch basin was installed too. The finished product will be ready to show off shortly. Please keep in mind we will have to keep foot traffic off the newly sodded area for a while. Please walk up cart path to access putting green.