As promised, the shapers arrived only a couple days ago, but three bunkers are already complete and ready for the final phase! With good weather forecasted once again next week, holes 1, 2 and 3 will be completed with shaping!
Our BHCC crew will be hard at work tapping into the final phase, phase 4! Drainage, bunker liner and sod will be installed behind shapers. It's important to get these materials in place before any significant rain. Bunker sand can be added at a later time to prevent getting too behind keeping up with the shapers.
Next week will bring some outstanding results, so stay tuned!